DB Engineering supplied AVK valves and provided installation and operation guidance for the 60,000 m³/day My Le Booster Pumping Station.
DB Engineering scope
Supply of AVK valve equipment and installation and operation guidance for the My Le Booster Pumping Station with a capacity of 60,000 m³/day.
Project progress
The My Le Booster Pumping Station was completed and put into operation on 31 May 2024. Remaining works are being accelerated and were scheduled for completion in the third quarter of 2025.
For the 2026-2030 period, BIWASE Long An plans to increase system capacity to 300,000 m³/day.